Clients Mogas Uganda Ltd Services Construction Start and Completion Date March 2014 live preview Rehabilitation of Mogas Fuel Depot on Plot 94-100, Jinja Road, Band Earthworks, construction of perimeter fence, asphalt paving works, retaining walls construction and drainage works Concrete to the Off-loading Slab Form Work to Retaining Wall Form
Clients ABB Limited Services Construction Start and Completion Date Nov.2017 To Jan.2018 live preview Assembly of New Reactor No.2 at Kampala North, UETCL Substation UGABB/PO 139/2017 Installation of 1x40MVA 11kV Current Limiting Reactor and refurbishment of damaged 1x40MVA 11kV Current Limiting Reactor at Kampala North Substation in collaboration with ABB
Clients Umeme Limited Services Construction Start and Completion Date June 2015 To Dec.2015 Construction of New Substation at Namugongo on a Turn Key Basis Babcon Uganda Limited in Joint Venture with ABB Limited IFB/LB/CCD/0016 Design and build; two transformer plinths, a firewall, cable trenches, plant house and guard house,
Clients ABB Limited Services Construction Start and Completion Date July 2016 To Dec.2016 live preview Civil Works and Installation of 2 No 42/60mva transformers at Nalubaale 132/33 kV Power Substation. UGABB/PO080/2016 Civil works and installation of 2 No 42/60mva transformers and including cable trenches Nalubaale 132/33kv power substation for Eskom
Clients Umeme Limited Services Construction Start and Completion Date March 2016 To Dec.2016 Construction of New Substation at Moniko, Lugazi on a Turn Key Basis Babcon Uganda Limited in Joint Venture with ABB Limited IFB/CB/CCD/0021 2/20MVA 33/11 Transformers , 2x100KVA 33/0.45kV Transformers complete with a Transformer Bay, 11Kv Indoor Switchboard,
Clients Uganda Electricity Company Ltd Services Construction Start and Completion Date January 2018 To May 2020 live preview Design, Manufacture, Deliver, Installation of 1x32/40MVA,132/33kv Power Transformer 132kV Transformer Bay & Accessories at Kampala North (UETCL) Substation, Proc.Ref: UETCL/SUPLS/2016/00052 132/33kV 40MVA Power transformer, 132kV Outdoor switchgear and busbar system, refurbishment of
Clients Eskom Uganda Limited Services Construction Start and Completion Date Feb 2020 To Dec 2020 live preview Refurbishment of Switch yard Towers and Concrete Substructures in the Substation Contract No. RTO/413032 Refurbishment of the steel support structures in the 33kV, 132kV substations and 132kV extension switchyard. Repair of the deteriorated
Clients Eskom Uganda Limited Services Construction Start and Completion Date October 2020 To June 2021 live preview Remediation of Stair Cases For Unit 1, 5 and 9 at Nalubaale Power Station Procurement Ref.No. RTO/413606 Design of steel beams supporting the staircases Fabrication and Galvanizing of steel support members Concrete repair
Clients Eskom Uganda Limited Services Construction Start and Completion Date August 2021 To January 2022 live preview Design and Construction of the New Generator Transformer Plinths for Unit 3 and 5 Contract No.RTO/ 414459 Design of new transformer plinths; Preparation of architectural drawings, Conducting of geotechnical investigations, and Structural designs
Clients Ministry of Energy and Mineral Development/Rural Electrification Program (REP) Services Construction Start and Completion Date July 2020 To August 2022 live preview Engineering, Procurement and Construction of Muzizi B Substation and Power Evacuation Lines for Bukinda and Lower Nkusi Hydropower Projects in Kibaale District- Lot B: Supply and